Manufacture of bricks |
To minimize
breakages in cold weather, increase the cement content of the mix or the curing
period before moving blocks.
Ordering and
stockpiling materials
Aggregates
and cement should be ordered in good time. Stocks should be sufficient to
prevent stoppages due to lack of material.
As a rough
guide, using an aggregate: cement ratio of 8:1 by loose volumes, three and a
half bags of cement and a cubic meter of aggregate will be enough to make about
400 bricks. The number of blocks produced from the same quantity of material
will depend on block size and whether they are solid or hollow.
Aggregates
must be stockpiled in such a way that contamination is prevented and mixing of
different types is prevented.
Cement must
be stored in such a manner that it is kept dry. Cement in bags should be used
within one month of being delivered.
Batching
Cement, if
supplied in bags, should preferably be batched by the full bag. Cement supplied
in bulk may be weighed (preferable) or batched by loose volume (not
recommended).
It is
important to batch all materials accurately. Batching containers, e.g.
wheelbarrows, buckets, drums and wooden boxes, should be loosely filled to the
brim and struck off flush with it. To avoid errors, there should be enough
containers for a full batch to be made without using any container more than
once. Dented or broken containers must not be used. The amount of water to be
added to the mix is judged by eye and by doing some simple tests
Water
content
Water
content is critical. The mixture must be wet enough to bind together when
compacted, but it should not be so wet that the blocks slump (sag) when the
mould is removed. A common mistake is the use of mixes that are too dry,
resulting in incomplete compaction. The moisture content should be as high as
possible as this allows better compaction and thus gives the best strength.
Mixing
Hand mixing
with the use of shovels should be done on a level concrete slab or steel plate.
First spread
the sand out 50 to 100 mm thick. Then distribute the cement, and stone if any,
evenly over the sand. Mix aggregate and cement until the color is uniform.
Spread the mixture out,
sprinkle
water over the surface and mix. Continue with this process until the right
amount of water has been mixed in.
Molding
Hand
operated machines should be used as instructed by the manufacturer.
The mould of
a powered machine should be filled until approximately six to eight cycles of
compaction are required to bring the compacting head to its stops. Too little
or poor compaction should be avoided as it results in greatly reduced
strengths.
Curing
Curing is
the process of maintaining a satisfactory moisture content and a favorable
temperature in the blocks to ensure hydration of the cement and development of
optimum strength.