Tuesday, July 16, 2013

Retardation/Hot Weather Concrete

Retardation/Hot Weather Concrete
Retardation/Hot Weather Concrete
The concrete should be protected from drying out during handling.
Concreting is only possible at high temperatures if special protective measures are provided. These must be in place from the start of concrete production to the end of curing. They are dependent on the outside temperature, air humidity, wind conditions, fresh concrete temperature, heat development and dissipation and the dimensions of the pour.
The fresh concrete must not be hotter than +30°C during placement and installation without these protective measures.
Possible problems
Working with non-retarded concrete can become a problem at air temperatures over 25°C.
·     Hydration is the chemical reaction of the cement with the water. It begins immediately on contact, continues through stiffening to setting (initial set) and finally to hardening of the cement paste.
·     Each chemical reaction is accelerated at a higher temperature.

This can mean that correct and complete compaction is no longer possible.
The normal counter measures are the use of retarded super plasticizers or super plasticizers combined with a set retarder.
Retardation terms and dosing tables
Purpose of retardation: To extend the working time at a specific temperature.
Working time: The time after mixing during which the concrete can be correctly vibrated.
Free retardation: The initial set is certain to start only after a specific time.
Targeted retardation: The initial set is started at a specific time.


No comments:

Post a Comment